The connection of the Hydro One Dinorwic Junction transmission network and the Pickle Lake substation carried out by our High Voltage team, as part of the Wataynikaneyap electricity transport project, was undertaken to address a critical need for electricity access in 17 isolated First Nations communities in Ontario.

This ambitious and innovative project involved a series of major works to establish a reliable and sustainable electrical infrastructure in often hostile environments, while reducing dependence on diesel generators, thus promoting sustainable development and improving the quality of life for local populations. Initiated by Wataynikaneyap Power, a company majority-owned by 24 First Nations in partnership with Fortis Inc. and other private investors, the project aimed to replace aging diesel generators, unable to meet the growing demand for energy, with a more reliable and environmentally friendly source of electricity.

New Reliable and Sustainable Installations

The main components of the project included the installation of nearly 300 kilometers of 230kv overhead transmission lines, stretching from Dinorwic to Pickle Lake in northwestern Ontario. New transmission connection facilities were erected in the Dinorwic region, along with a new transformer station in the township of Pickle Lake. These works required a 40-meter-wide deforested area to accommodate the poles and wires of the power transmission line, as well as a 2-kilometer-wide corridor for construction activities.

Services provided by our team as part of this project are as follows:

  • Detailed design civil, electrical, structural and protection & control; drawings signed and sealed by PEO engineer;
  • Bill of Materials (BOM);
  • Approve vendor drawings, bid evaluation and equipment specifications;
  • Studies and calculations;
  • Client liaison (utilities & IESO);
  • Remote and On-Site Field Support.

L’innovation au cœur de la réussite de ce projet

En introduisant la technologie la plus récente dans le domaine du contrôle et de l’exploitation à distance des équipements à haute tension, le projet a pu bénéficier de solutions avancées pour assurer la fiabilité et l’efficacité opérationnelle des infrastructures électriques.
De plus, la conception de l’infrastructure de la sous-station a fait appel aux outils de conception les plus récents et les plus puissants pour les activités civiles, assurant ainsi une performance optimale même dans les conditions climatiques rigoureuses du nord de l’Ontario. Les installations ont été conçues pour résister aux fortes tempêtes hivernales, avec une station sans personnel dotée de capacités de contrôle à distance, connectée au réseau de l’Ontario pour permettre un fonctionnement autonome sans nécessiter de déploiement de main-d’œuvre sur place pour les opérations quotidiennes.

Ce projet va bien au-delà de l’amélioration de l’approvisionnement électrique. Il s’agit d’une initiative porteuse de prospérité économique et de stabilité sociale pour les communautés du nord, offrant des opportunités de développement durable et un avenir plus prometteur pour tous ceux qui en bénéficient.